Power transmission & distribution
Power and distribution transformers, reactors, bushings, insulators, switchgear, conductor and structural beams for towers and substations. This is the freight the US grid is short of, and lead times mean a delivery slip is not recoverable by paying more later.We plan these moves backwards from the energisation date: route survey and permit lead times first, then inland equipment, then the vessel, then the factory. Impact recorders and nitrogen pressure are checked at handover points, crates are specified for a multi-modal journey, and the utility or EPC receives documentation in the format their commissioning team actually needs.